Tetrosyl RBR Portal Frame Building Extension

Client :

 

Nature of the works :

 

 

Scope and service provided :

 

 

 

 

 

 

 

Duration :

Tetrosyl, Royle Barn Road

 

Design and build project.
Steel portal framed, steel clad building extension with rapid door opening.

 

STEM Construction were commissioned to complete:

  • Procurement and coordination of the design process
  • Procurement of the steel framed structure, 20m x 19m x 9m
  • Procurement and installation of the steel cladding to match existing of the original building
  • Procurement of the rapid opening roller shutter door
  • Drainage alteration to suit new layout
  • Alterations to the existing building to enable connection to the new
  • Installation of Armco barrier walkways and building protection
  • Procurement and management of the lighting installation

 

6 weeks on site construction period