FCC Environmental
Client :
Nature of the works :
Scope and service provided :
Duration :
AE Yates / FCC Environmental
Kirklees CA Site
Waste Recycling Centre Modifications
Improvement works to the waste recycling facility whilst maintaining production of the waste recycling activities
STEM Construction was appointed to carry out:
- Excavation of grassed verges to enable the widening of the existing HGV access road and formation of HGV parking bays. The parking bays were formed using mesh reinforced concrete
- Breakout and disposal of the existing worn and degraded concrete slabs within the waste recycling sorting shed
- Reinstatement of the gas membrane layer
- Reinstallation of new mesh reinforced concrete slabs – 625 m2
- Removal of the existing precast concrete push wall segment from the waste storage areas. Replacement of damaged precast concrete segment and rebuild storage unit walls to new configuration
- Installation of new drainage system throughout the project area tying in the existing system
- Installation of new duct system for the project area tying into the existing network
12 week construction period