Bolton University Footpaths

Client :

 

Nature of the works :

 

 

Scope and service provided :

 

 

 

 

 

 

 

 

 

Duration :

AE Yates / Bolton Council / Bolton University

 

Section 278, Public Highway, Footpath Construction
The works was to construct a new macadam surfaced pedestrian footpath and tactile paved crossing points enabling easier and safer access to the new University building.

 

STEM Construction was appointed to:

  • Provide and maintain traffic and pedestrian management throughout the duration of the contract
  • Break out the existing footpath structure and kerb alignments. Remove all materials off site to a waste recycling facility
  • Construct a new vehicle access point into the proposed University development site and car park
  • Construct a new macadam surfaced footpath to the required revised levels including new kerb and edging alignment to the three sides of the University building
  • Installation of tactile paved crossing points
  • Raising all service manhole and inspection chamber covers to required new footpath levels
  • Supply and installation of Visirail pedestrian guard rails
  • Supply and installation of new road signage
  • Macadam surfacing of new vehicle access and footpath

 

8 week construction period